1、摘 要本设计为神华煤业公司2.40Mt/a矿区型选煤厂的初步设计,入洗原煤为一矿和二矿,入洗比例为75%:25%,两矿原煤均为焦煤。设计要求精煤产品满足灰分Ad=8.018.50%,水分Mt12.00%。本设计先对煤质资料进行分析、校正、计算,确定原煤是否分组、分级入选,并分析原煤的可选性。在此基础上,通过对几个可能的选煤工艺流程进行产品预测和技术经济比较,最终采用了三产品重介旋流器TBS粗煤泥分选浮选联合工艺流程。该厂原煤由皮带运至准备车间进行分级筛分,分级筛的筛孔为50mm,+50mm原煤进入破碎机,破碎后与分级筛筛下一起由皮带运至主厂房,进入有压三产品重介旋流器分选,0.5-0.25mm
2、粗煤泥进入TBS分选机,-0.25mm煤泥采用直接浮选。该设计选煤厂的主要产品指标如下:精煤:产率=87.09% ,灰分=8.03% ,水分=7.67%中煤:产率=2.68% ,灰分=36.61% ,水分=12.68% 矸石:产率=8.34% ,灰分=75.26% ,水分=14.00%煤泥:产率=1.86% ,灰分=46.37% ,水分=23.00%除工艺流程外,本设计还对选煤厂的建筑结构、供电和电气、机修车间、铁路运输、劳动定员、生产成本及建厂初步投资概算做了系统的设计。工厂工作制度为每年生产330天,每天工作16小时,两班生产,一班检修。全厂在籍人数184人,工程总投资18625.67万元
3、,吨煤投资77.61元,静态投资回收期为0.58年。全厂各车间各生产环节采用了先进的自动化检测装置,控制实行全厂集中控制与就近操作相结合的方法。为防止环境污染,该厂煤泥水系统实现洗水闭路循环,不外排生产废水。在粉尘和噪音污染严重的场所采取一定的除尘降噪措施。关键词: 选煤厂;设计; 重介 ABSTRACTThis is an initial design of Shen hua coking coal preparation plant with a capability of 2.40Mt/a . Raw coal comes from first mine and second mine,
4、 and the comparison of the two mines is 75%:25%.Both of the two mines are gas coal. The designed ash content of the clean coal ranges from 8.01% to 8.50% and the moisture is no more than 12.00%.After analyzing the date of coal samples and estimating of the quality of raw coal, it can be decided in c
5、hoosing the flowsheets of preparation with grouped row coal or sized row coal. Throw the comparison of techniques and economy on possible flowsheets, Heavy cyclone-Flotation combined separation process is selected as essential preparation process.The raw coal ,Transported by Leather belt, is to size
6、d by a Sizing screen in the prepare plant. The Sieve of the Sizing screen is 50mm.After Sizing, those material larger than 50mm will be processed in crusher. Then those materialwill be processed in Pressure three products heavy medium cyclone, those smaller than 0.25mm will be processed in direct fl
7、otation. And the rest will be processed in TBS(teeter bed separator).The products are as follow:Clean coal: Wt.=87.09% Ad=8.03% Mt=7.67%Middings: Wt.=2.68% Ad=36.61% Mt=12.68%Gangue : Wt.=8.34 % Ad=75.26% Mt=14.00%Slurry: Wt.=1.86 % Ad=46.37% Mt=23.00%Besides the process flowsheet,the building struc
8、ture,electricity supplying ,electronic situation , maintenance situation , the railway transportation, the number of worker, processes cost and the budgetary estimate of the primary invest of building of the plan and room are designed systematically in the project. The time of real production is 330
9、 days a year, 16 hours a day. That is, there are 3 working shifts per day in which two shifts for running and one for maintenance.184 workers are listed in this coal preparation plant. 18.62 million Yuan is invested in project and 77.61 Yuan per ton, the recovery period of investing is 0.58 year.The
10、 advanced automatic detecting devices are used in the plant. The approach to the machines is to combine the centralized controllmention with on the spot interlocking controllment.In order to avoid polluting the environment, this plant carry out closed water circuit without draing black water slurry
11、outside. Certain measures are conducted in decreasing the dust & noise pollution .The products are as follow:Keywords:coal preparation plant ; design; dense medium separation of wide range目录第一部分总论1第一节 矿区及厂址概况1一 厂区位置1二 厂区地理概况1三 矿区其它资源及其经济概况1第二节 选煤工艺1第三节 产品品种及用途2第四节 供水、供电2一 水源2二 电源2三 交通运输2第五节 主要经济技术指标
12、2第一章 建设规模、厂址及工作制度5第一节 选煤厂类型、厂型及厂址5第二节 工作制度5第二章 选煤工艺6第一节 煤质资料分析及可选性研究6一 煤质资料的审查6二 煤质资料的校正7三 煤质资料的分析8四 两矿原煤可选性研究及分组讨论17五 两矿煤质资料综合及分级讨论22第二节 选煤工艺的初定和技术经济比较29一 初步选定的方案分析29二 方案的产品预测30三 方案的技术经济比较37第三节 选定流程的介绍及流程计算39一 辅助工艺的确定39二 设计工艺流程的整体描述42第四节 流程计算44一 数质量流程计算44二 介质流程计算44三 工艺流程计算结果汇总54第五节 设备选型及计算56一 选型与计算
13、的原则和规定56二 主要设备选型与计算57第六节 选煤工艺布置68一 工艺布置原则68二 总平面布置68三 原煤来煤68四 主厂房68五 产品仓70六 尾煤系统70第七节 生产技术检查70一 检查的内容与项目70二 技术检查取样设置72三 检查室73第三章 建筑物和构筑物74第一节 概述74第二节 气象及地震资料74第三节 建筑物及构筑物设计74一 建筑设计74二 结构设计75第四章 给水排水76第一节 给水水源76第二节 用水量和水压76一 用水标准及用水量76二 水压76三 消防76第三节 给水系统76第四节 排水76第五章 生产辅助设施78第一节 机电修理车间78第二节 介质制备车间78
14、第三节 压缩空气供应79第六章 电气80第一节 供配80一 电源及供电方式80二 供配电系统80三 照明81四 防雷81第二节 集中控制与自动化81一 控制系统81二 控制原则81第三节 通讯调度82第四节 自动化82第七章 铁路运输83第一节 技术条件83第二节 股道设置83第八章 采暖通风与药剂库84第一节 采暖84一 概述84二 采暖温度84三 采暖方式84第二节 通风除尘84第三节 室外供热管道85第四节 药剂库、油脂库85第九章 工业场地总平面86第一节 原始资料86第二节 总平面布置86一 布置原则86二 场地功能区分86三 总平面布置86四 辅助车间的布置86五 行政、生活福利设施的布置87六 运输87七 场地利用系数及绿化87第十章 技术经济88第一节 劳动定员88第二节 选煤成本90一 产品销售收入90二 分离前成本90三 分离后成本91四 财务分析92第十一章 环境保护93第一节 环境保护设计依据及采用的环境保护标准93一 环境保护设计依据93二 采用的环境保护标准93第二节 选煤厂污染防治措施93第三节 厂区绿化93第十二章 劳动安全94第一节 预防自然灾害措施94第二节 防火防爆措施94第三节 防机械伤害和人身安全措施94第四节 防触电伤害措施94第二部分第一章 概算编制说明95第一节 工程概况及投资范围95第二节 编制依据及取费标准95一 编制依据95